21 |
Standardization of guidelines for illumination of airports through decorative lighting on special occasions -reg. |
Different procedures have been adopted for award of works e.g. call of quotations (physical mode)/open tender (CPP portal) with different work experience criterion. |
Technical Instruction No. 143 dated 27.02.2024 |
|
22 |
Systemic Improvement – Admissibility of CATC Instructor & OJT Instructor allowance |
As per existing guideline, It is not clear whether the Principal CATC is eligible for payment of Instructor Allowance though Principal CATC not engaged in instructional duties. |
Corporate HRM Circular no 05/2024 dated 13.02.2024 |
|
23 |
Calculation of Monthly Price Index for Civil Components, E&M Components and Material percentage details to be filled in Schedule-F for Price adjustment under Clause -10 CC reg. |
As per prevailing General Conditions of Contract, the contract clause for adoption of monthly price Index for Civil and Electrical component is not clear. |
Technical Instruction no.141 dated 07.02.2024. |
|
24 |
Systemic Improvement- Issue of Commissioning Certificate / Completion Certificate. |
CTEO during investigation of a work had made observation that commissioning and final acceptance letter has not been issued upon completion of a work for particular site. |
Circular No.02/2024 Dated 08.01.2024 |
|
25 |
Systemic Improvement – Preparation of tender terms & conditions. |
CTEO during investigation of a work had made observation in respect of a clause ‘With- holding and lien in respect of sums due from contractor’ wherein it was mentioned that ‘Provided that the AAI shall not be entitled to recover-any sum overpaid, nor the contractor shall be entitled to payment of any sum paid short where such payment has been. agreed upon between the Executive Director Airport Systems/General Manager Airport Systems on the one hand and the contractor on the other under any term of the contract permitting payment for work after assessment by the Executive Director Airport Systems/ General Manager Airport System ‘ gives discretionary powers to AAI officials. |
Circular No.01/2024 Dated 08.01.2024 |
|
26 |
Transaction in Movable/Immovable Property |
Permission to acquire immovable properties was not being processed through personal files instead it is processed in separate files by the Airports where he was posted at that point of time. If all the premissions/ sanctions are processed through the personal file of each employee, it is retained till superannuation of employee wherever the official is posted. Considering this, it is suggested to take up with HR Department to make a policy that henceforth all the issues related to acquisition of movable / immovable property sanctions/ permissions is required to be handled through the personal file of respective employee so as to ensure that these vital documents remain available till superannuation of the employee. |
CHRM Circular No. 39(a)/2019 dated 01.11.2023. |
|
27 |
Systemic improvement measures as suggested by Vigilance Dept. |
i) During course of CTE /CTE type inspection of Engineering works, multiple issues requires systemic improvement to avoid reoccurrence of such lapse in future. |
Technical Instruction no. 137 dt 23.10.2023 |
|
28 |
Turn Over Criteria in IT Tenders |
It was recommended that clearer & more specific guidelines may be issued regarding which conditions of MEITY guidelines will be adopted in lT tenders. Such specific guidelines could bring out:
a)Name of specific lT works for incorporating the particular criterion from MEITY guidelines e.g. Related Turnover/ Net Sales Turnover etc'.
b)Clarity on the participation of the minimum number of Bidders in the lT Tenders, while adopting of MEITY guidelines. |
Circular No.02/2023 dated.20.10.2023 |
|
29 |
Systematic improvement related to the work experience criteria in the tender for the Services/AMC. |
ln case the tender is called for Services/AMC, to be provided for more than 01 year, past work experience criteria from the prospective bidders is decided on the basis of cost of Services /AMC for complete period whereas it should be considered for 01 year only to enhance competitive bidding |
Technical Circular No. 01/2023 dt. 18.09.2023 |
|
30 |
Monitoring of project works through PMC and execution of Extra/ Substitute Items by AAI. |
i) Projects was monitored by Project Management Consultant (PMC) ,but then the question arises as to who monitors PMC and how effective that monitoring is.
ii) As per clause-12 of the contract agreement, the Engineer-in-Charge of AAI was given power to make alteration in, omissions from, additions to, or substitutions for the original specifications, drawings, designs and instructions that may appear to him to be necessary or advisable during the progress of work. This gives a broad, general and sweeping power to Engineer-in-Charge. Thus, the Engineer-in-Charge may make such alterations/ additions/ omission/ substitution in the original specifications, drawing, design and instruction that the whole character/ basic features and objectives of the project may be lost without the knowledge of Tender Approving/ Competent Authority. |
Technical Instruction no. 125 dt 12.07.2023 |